Capacity Bets Meet the Demand Test
Filatex advances Rs. 690 crore expansion toward October completion, but cautious buying leaves utilisation to prove the return
Cosmo plans 50% rigid-packaging capacity growth with little capex, but utilisation and mix must do the heavy lifting
Garware commits Rs. 191 crore to solar-control film capacity, but the supply arrives only in H1 FY28
The Silvassa addition and an 80%-utilised Punjab polymerisation unit now face a commissioning and demand test
All Time Plastics adds 14 machines and 1,500 tonnes, but its 75% utilisation target still depends on demand
Deepak Chem Tech commissions a Rs. 735 crore MIBK-MIBC plant, but customer ramp-up now replaces construction risk
Chemplast adds 7,000 tonnes of paste-PVC capacity, but monsoon demand and pending anti-dumping relief limit the near-term lift
Berger indicates Rs. 600–800 crore FY27 capex, but key plant work begins near the fiscal-year end
Terminals, Tanks and Refinery Decisions
Aegis awards Rs. 142.5 crore JNPA propane-tank work, but the filing leaves completion and handover dates open
Aegis puts Rs. 37.17 crore into Kochi liquid-storage works, but related-party execution still needs commissioning proof
Indian Oil reviews Rs. 33,023 crore Nagapattinam plan as petrochemicals challenge the greenfield refinery case
BPCL makes 47 deep boreholes and seismic testing the design gate for its proposed Kandla LPG terminal
Safety and Asset Resets
National Oxygen runs Puducherry gas capacity full, but proposed asset sales point to a smaller operating footprint
Chemplast contains the Karaikal EDC fire without stopping paste PVC, but imported feedstock raises the continuity cost test
Contracts Under the Execution Lens
HPCL pushes Visakh VR CDU3 optimisation into plant implementation while tender timelines remain internally inconsistent
Mecon undercuts EIL by 77.4% for GAIL pipeline consultancy as lump-sum execution risk shifts to L1
IOCL transfers Paradip hazardous-waste transport and treatment risk without guaranteeing minimum contract throughput
BPCL’s Kochi metallography contract combines specialist integrity work with no guaranteed call-off volume
CPCL makes ultrasonic correlation and shutdown speed the performance test for heater intelligent pigging