Bulletin Updates
Bina Refinery Updates: Today roundup – 28 Aug 2025
Aug 28, 2025
Retendered API-610 pump package resets man-days and multi-group award math for BPCL’s BPREP
BPCL has pushed out a refreshed RFQ. A for horizontal centrifugal API-610 pumps at Bina. EIL has locked commissioning man-days and tightened commercial inclusions, while warning that L1 can reshuffle on a least-cost combination. The files imply a retender clean-up, but the explicit cancellation memo is not in the packet.
Sixteen bidders chase BPCL’s clad column package for Bina refinery-petchem expansion
BPCL’s Bina expansion tender for LAS/SS clad columns drew 16 bidders under EIL management. A zero-deviation regime, heavy ABG-linked payments, and a Rs 15 lakh EMD underscore tightened procurement norms. The high metallurgy entry bar ensures only fabricators with prior clad vessel track record remain in play.
ITT undercuts peers by 18% in BPCL Bina pump tender managed by EIL
BPCL’s Bina Petchem pump package saw ITT India quoting Rs 5.65 crore against Flowserve and Kirloskar’s ~Rs 6.7–6.8 crore. Multiple extensions hinted at bidder hesitation over PQCs and scope splits. EIL’s strict document verification policy signals a tightening risk posture.
Vijay Tanks wins BPCL Bina sphere package as EIL enforces strict PQCs and shifts CPBG, GST risk
BPCL’s Bina sphere package drew only three proven storage contractors under EIL’s watch. Vijay Tanks slashed bids nearly 20% below peers, exposing margin risks. With GST ITC deleted and CPBG timelines tightened, the contract structure signals tougher PSU cost-policing.