Contractors must complete full geotech survey—including 20m bores, triaxial and resistivity… – CBG contracting: Round-up of the day, 1 Jul 2025
Jul 01, 2025
BPCL’s Hubli CBG geotech tender sets 45-day race amid terrain, test overload, and safety chokeholds
Contractors must complete full geotech survey—including 20m bores, triaxial and resistivity tests—within 45 days on a hilly, tree-covered site.
With no EMD but heavy retention, PVCs, and certified DG setup clauses, only pre-mobilized firms can survive the timeline pressure.
BPCL’s Mysore CBG survey tender drops EMD, adds dense compliance and a 45-day clock
Despite waiving EMD and ePBG, BPCL’s Mysore CBG plant survey tender loads the bidder with over 20 mandatory soil and survey tests, ultra-fast completion, and complex site entry protocols — making readiness, not liquidity, the new hurdle.
BPCL’s Bhilai biogas project sees major technical scope resets, land risk offload to bidder
Multiple corrigenda have overhauled the Bhilai MSW-to-CBG tender—shifting soil and topo liabilities to the contractor, expanding proof requirements for technical credentials, and tightening control over OEM brand approvals.
The pattern of repeated bid extensions suggests deep-rooted contractor concerns.