Project Event: The RFQ for the EPC contractor has been released. Initially, the bid due date… – Software update: Fertilizer projects, 10 Jun 2025
Jun 10, 2025
Ammonia Revamp Project
Cost: Rs. 910 Cr.
Project Event: The RFQ for the EPC contractor has been released. Initially, the bid due date was April 18, 2025, which was first extended to May 17, 2025, and then to June 19, 2025. It has now been further extended to June 27, 2025, due to the continued lack of suitable bidders. Meanwhile, a study focusing on the revamp of Ammonia Lines I and II to enhance energy efficiency has been completed, and the final report has been submitted.
Effluent Treatment Plant Upgrade Project
Cost: Rs. 100Cr.
Project Event:RFQ for the Design, Supply, and Installation of HRSCC for Water Treatment Plant has been out, and the bid due date is July 19, 2025. In response to ongoing queries from prospective bidders, the bid submission deadline for the Effluent Treatment Plant (ETP) Upgrade Project has been extended to June 10, 2025. This marks the fourth extension from the original deadline of March 18, previously revised to April 8, April 18, and May 2. The extension reflects the project's continued commitment to a transparent and well-informed LSTK contractor selection process.
Ammonia Storage Tank +Refrigeration
Cost: Rs.100Cr.
Project Event: The tender for the Lump Sum Turnkey (LSTK) contractor to construct the proposed 2500 cubic meter ammonia Horton Sphere storage facility has not yet been released. Although the original bid submission deadline was March 25, 2025, the technical bid opening did not take place due to a lack of suitable bidders meeting the technical criteria. As a result, the hiring process is currently on hold. The tender is now expected to be reissued with revised specifications in May 2025 and is likely to be released in July 2025.
SSP/GSSP /Sulphuric Acid Project
Cost: Rs.72Cr.
Project Event:The company has submitted the final EIA report and is currently awaiting Environmental Clearance (EC), which is anticipated by the end of July 2025. Internal discussions with shortlisted LSTK contractors have progressed further, and the RFQ for the LSTK contract is now expected to be issued in September 2025.