Project Event: The project is advancing steadily, with overall completion now at 67.10% and… – Software update: Fertilizer projects, 24 Apr 2025

Apr 24, 2025

Ammonia-Urea Brownfield Project

Cost: Rs. 16372Cr.

Project Event: The project is advancing steadily, with overall completion now at 67.10% and the OSBL scope already 80.89% finished. Key civil and structural milestones have been met: the Coal Gasification Frame has reached the 5th of 7 floors, the UreaMainFrame stands at the 4th of 5 floors, the PrillingTower has risen to 106m of its 123m target, and formwork is under way at the 11m level for all six cells of the 17mtall UreaCoolingTower. Recognizing schedule pressure, PDIL has recommended a provisional extension to the LSTK contractor, WECL, and is issuing an addendum to the DFR to quantify any cost impacts. With major structures well advanced and proactive timeline and costmanagement measures in place, the project remains on a clear path toward the timely completion of the remaining works.

Phosphoric acid Expansion Project

Cost: Rs. 500Cr.

Project Event:Project activities are still on hold and are now expected to resume in Q32025. Because of internal matters, the RFQ for the LSTK contractor is also likely to be issued in Q32025.

The full story is for subscribers. Log in to read it, or start a free trial.
Log in Start a free trial »