Project Event: The project is still in the initial phase, and the company is awaiting… – Software update: Fertilizer projects, 10 Apr 2025

Apr 10, 2025

Ammonia-Urea Expansion Project

Cost: Rs. 6505Cr.

Project Event: The project is still in the initial phase, and the company is awaiting environmental clearance. Meanwhile, internal discussions are ongoing regarding the Request for Quotation (RFQ) for the Project Management Consultant (PMC) contractor. The RFQ is now expected to be released in Q3 2025.

Ammonia Make-Up Gas Loop Project

Cost: Rs. 100 Cr.

Project Event:Finalization of the EPC contractor is in its advanced stage, while Topsoe is nearing completion of the Basic Engineering Package (BEP). Procurement of proprietary equipment is underway, with orders already placed for critical long-lead items. The project remains on track for completion in Q1 FY 2027-28.

The full story is for subscribers. Log in to read it, or start a free trial.