Project Event: Procurement activities remain delayed due to continued financial stability… – Software update: Fertilizer projects, 19 Mar 2025
Mar 19, 2025
NPK-TSP-GSSP Greenfield Project
Cost: Rs. 100Cr.
Project Event: Procurement activities remain delayed due to continued financial stability challenges. However, progress has been made with issuing the Request for Quotation (RFQ) for the technology license and LSTK contractor in May 2025.
SSP/GSSP/PSSP Greenfield Project
Cost: Rs. 100Cr.
Project Event:"The RFQ for the LSTK contractor is now expected to be released in Q2 2025 due to delays in internal discussions. The project has already obtained environmental clearance.