Bulletin Updates
Project Event:The feasibility study consultant evaluation is still ongoing. It is likely to… – Software update: Fertilizer projects, 7 Mar 2025
Mar 07, 2025
Phosphoric Acid & Sulphuric Acid Greenfield Project
Cost: Rs. 1800Cr.
Project Event: Detailed engineering is still ongoing. The RFQ for the EPC contractor is likely to be released in May 2025. Vendor selection for major equipment has been initiated, and detailed engineering is progressing, utilizing TECI's and Chemetics' Basic Engineering Packages received earlier in 2024.
Urea Revamp Project
Cost: Rs. 450Cr.
Project Event:The feasibility study consultant evaluation is still ongoing. It is likely to be finalized in mid-2025. The sanctioned term loan of Rs. 300 crores from HDFC Bank continues to support preliminary activities, including site surveys and regulatory approvals.