Bulletin Updates
Project Event: The contractor for providing and fixing rolling shutters and handrailing in… – Software update: Fertilizer projects, 6 Mar 2025
Mar 06, 2025
Briquette Fired Boiler Green field Project
Cost: Rs. 27Cr.
Project Event: The contractor for providing and fixing rolling shutters and handrailing in the Briquette-Fired Boiler Plant has been Finalized. Construction and installation are progressing steadily. Given the current pace, the project is expected to be commissioned by the end of April 2025.
Cobalt Recovery Unit Greenfield Project
Cost: Rs.100Cr.
Project Event:The company is in the final stages of selecting the LSTK contractor for the cobalt recovery project. The selection process has been extended, and the contractor is now expected to be finalized by April 2025. Internal discussions and technical evaluations are ongoing to ensure optimal process efficiency and project execution.