Coal to Ammonium Nitrate Greenfield Project
Cost: Rs. 11782Cr.
Project Event: The bid submission deadlines for the Ammonia Synthesis Plant and the Nitric Acid & Ammonium Nitrate project under the JV have been extended once again. Initially set for February 28, 2025, they have now been pushed to March 31, 2025, due to insufficient suitable bidders.
SSP/GSSP Greenfield Project
Cost: Rs. 59Cr.
Project Event:The company has submitted all necessary documents to the environmental clearance authority, and approval is awaited. The clearance is expected in Q2 2025. Initially, the RFQ for the local contractor was expected to be finalized by the end of Q1 2025; however, due to internal discussions, it is now likely to be released in Q2 2025.