Project Event: The Project has been delayed. Ongoing financial constraints and prolonged… – Software update: Fertilizer projects, 18 Feb 2025

Feb 18, 2025

Ammonia/Nitric Acid/SOP Greenfield Project

Cost: Rs. 200Cr.

Project Event: The Project has been delayed. Ongoing financial constraints and prolonged negotiations with multiple contractors have pushed the finalization timeline. The company now expects to finalize the contractor by mid-2025. This delay may impact the overall project schedule.

Phosphate Rich Organic Manure Greenfield Project

Cost: Rs. 100Cr.

Project Event:The project remains in the evaluation phase. The submission of the environmental clearance proposal, initially expected in Q4 2024, has been delayed and is now likely to be submitted in Q2 2025. Consequently, the release of the RFQ for the feasibility study, which was planned for the end of Q1 2025, is expected to be pushed to Q2, 2025.