New NPK Train Greenfield Project
Cost: Rs. 56Cr.
Project Event: Due to pending approvals, the project remains in its early stages. MFL is expected to hire a feasibility consultant in Q3 2025.
Nano Urea Greenfield Project
Cost: Rs. 220Cr.
Project Event:The engineering work has been completed, and the procurement of long-lead equipment (such as reactors, pumps, and storage tanks) is in progress or finalized. Site mobilization is underway, and civil work, including foundation laying, excavation, and structural framework, may have started. The project remains on track for September 2025 commissioning, barring any delays in equipment delivery, construction progress.