Project Event: 60 % of the construction work has been completed, Comprehensive basic and… – Software update: Fertilizer projects, 5 Feb 2025
Feb 05, 2025
Sulphuric Acid Greenfield Project
Cost: Rs. 200Cr.
Project Event: 60 % of the construction work has been completed, Comprehensive basic and detailed engineering package for the Alkali Scrubber has been completed. the project has completed major civil work, progressed with equipment installation, advanced piping, and electrical work, and begun mechanical completion for some sections. The 23 MW Captive Power Plant should be under advanced construction, with turbine and generator installation in progress. Pre-commissioning activities may start by mid-2025, keeping the project on track for commissioning by the end of 2025.
Nitric Acid Storage Tank Greenfield Project
Cost: Rs. 50 Cr.
Project Event:The project is still on hold due to an internal matter, It will likely reactivate in Q2, 2025