TAN and CNA Expansion Project

Cost: Rs. 50 Cr.

Project Event: The project has prepared the Terms of Reference (ToR) for obtaining environmental clearance, and internal discussions are currently underway. The RFQ for the LSTK contractor is expected to be issued in Q2 2025.

DAP Expansion Project

Cost: Rs. 649 Cr.

Project Event:The company is currently undergoing environmental clearance, marked as "Intimate." The EC authority has requested modifications and clarifications for the proposal. The RFQ for the LSTK contractor is expected to be released by May 2025.