Jan 27, 2025
Granular Single Super Phosphate Greenfield Project
Cost: Rs. 148 Cr.
Project Event: The Discussions with local contractors have advanced, and internal matters related to hiring are being resolved. The selection of the LSTK contractor is nearing completion, with finalization expected by March 2025
GSSP/GBSSP/GZSSP/GPG/BSP/BSG Expansion Project
Cost: Rs. 48 Cr.
Project Event:The RFQ for the LSTK contractor is expected to be released in Q2 2025. Due to delays in internal discussions, the company is currently in talks with a local contractor. Additionally, the project has already received environmental clearance.