Project Event: Overall, 80% of the constriction work has been completed, with key… – Software update: Fertilizer update, 26 Dec 2024
Dec 26, 2024
Ammonia Storage Tank Greenfield Project
Cost: Rs. 100 Cr.
Project Event: The project has completed the feasibility study, and the RFQ for the LSTK contractor is expected to be released in Q1 2025. The timeline has been revised to accommodate the resolution of internal discussions and align with project requirements.
Sulphuric acid Plant Greenfield Project
Cost: Rs. 182 Cr.
Project Event: Overall, 80% of the constriction work has been completed, with key installations, including the sulfur burner and acid towers. Mechanical completion is on track, and pre-commissioning activities are expected to commence in January 2025. The commissioning timeline remains February 2025.