Ammonia Revamp Project
Cost: Rs.200 Cr.
Project Event: The finalization of the EPC contractor is ongoing. It is expected to be finalized by the end of Q1 2025. Topsoe, Denmark, has also initiated the delivery of the Basic Engineering Package (BEP) and the procurement process for proprietary equipment is on track. The project remains on schedule, with completion targeted for the first quarter of FY 2027-28.
Green Hydrogen Project
Cost: Rs.1291 Cr.
Project Event: The project is under development. The RFQ for the feasibility study consultant is likely to be released in Q1 2025, The contract is expected to be awarded by Q1 2025.