SSP/GSSP/PSSP Greenfield Project
Cost: Rs.100 Cr.
Project Event: The project has obtained environmental clearance, and internal discussions are currently underway. The RFQ for the LSTK contractor is expected to be issued in Q1 2025. Civil work for the project has already been completed.
Ammonium Phosphate Potash Sulphate Greenfield Project
Cost: Rs.50 Cr.
Project Event: The project is still under clearance of environmental, the company is continuously replying to the ADS raised by the environmental authority, The environmental clearance is likely to be granted by April 2025. RFQ for the LSTK contractor is expected to be released in Q2 2025.