Project Event: The project is 75% complete, procurement 95% complete, civil construction 85%… – Software update: Fertilizer update, 13 Dec 2024

Dec 13, 2024

NPK-TSP-GSSP Greenfield Project

Cost: Rs.100 Cr.

Project Event: Procurement activities are still pending due to ongoing financial stability challenges. However, the issuance of the Request for Quotation (RFQ) for the technology license and LSTK contractor is now expected to occur in early Q1 2025

Nano Urea Green field Project

Cost: Rs.257 Cr.

Project Event: The project is 75% complete, procurement 95% complete, civil construction 85% complete, mechanical erection and installation 70% complete, and electrical and instrumentation 60% complete. Testing and pre-commissioning are scheduled for Q1 2025; the project remains on track for commissioning by April 2025.