RFQ for the DPR consultant is likely to be floated in Q1 2025 – Power projects: Update, 3 Dec 2024
Dec 03, 2024
Rs. 6500 crore super-critical thermal power expansion project: RFQ ahead
TOR has been granted.
Allocation of land is yet to be finalized.
RFQ for the DPR consultant is likely to be floated in Q1 2025
Rs. 8000 crore greenfield pumped storage project: RFQ ahead
Geotechnical investigation and topographical survey works have been completed
FC (stage-1) is under the approval stage
RFQ for the PMC is likely to be floated in January 2025