Project Event: The project elicited the environmental clearance on November 4, 2024. The…
This edition covers:
- Cost : Rs. 6433.52 Cr.
- Project Event : The project elicited the environmental clearance on November 4, 2024. The internal discussion is ongoing. The RFQ for the LSTK contractor is likely to be released at the end of December 2024.
- Cost : Rs. 300 Cr.
- Project Event : Due to delays in the evaluation process, the project is currently in the tendering phase. The LSTK contractor is expected to be finalized by the end of January 2025. Additionally, the company has engaged Kerney as its Strategic Management Consultant.
The complete bulletin is available to subscribers.