Bulletin Updates

Project Event: Due to a lack of suitable bidders, the bid due date for the LSTK contractor… – Software update: Fertilizer update, 15 Nov 2024

Nov 15, 2024

Effluent Treatment Plant Upgrade Project

Cost: Rs. 100 Cr.

Project Event: Due to a lack of suitable bidders, the bid due date for the LSTK contractor has been extended from November 12 to December 3, 2024.

Roof Top Solar Power Project

Cost: Rs. 10 Cr.

Project Event: The hiring process for the LSTK contractor is still on hold due to a lack of suitable bidders. The RFQ for the LSTK contractor is likely to be re-released at the end of December 2024.