Phosphoric acid/Sulphuric acid Greenfield Project

Cost: Rs.1000 Cr.

Project Event: The project is currently advancing through the early construction and detailed engineering stages. The detailed engineering study is in progress and is anticipated to be completed by February 2025. The release of the Request for Quotation (RFQ) for the Lump Sum Turnkey (LSTK) contractor is expected in the first quarter of 2025.

DAP/Phos Acid Greenfield Project

Cost: Rs. 54 Cr.

Project Event: The terms of reference proposal have been approved, and the application for environmental clearance is expected to be granted by April 2025. The Request for Quotation (RFQ) for the local contractor is anticipated to be issued in the second quarter of 2025.