- Cost : Rs. 110 Cr.
- Project Event : The term of references proposal has been accepted, but the environmental clearance proposal has not yet been submitted. The RFQ for the contractor is expected to be released in Q1 2025.
- Cost : Rs. 6433.52 Cr.
- Project Event : The company is actively working to address concerns raised during the public hearing and is engaging with local authorities to resolve issues related to the protests. Discussions with stakeholders are ongoing to facilitate a smooth environmental clearance (EC) approval process. RFQ for the LSTK contractor is likely to be released in April 2025.