Project Event: The feasibility study is ongoing, and RFQ for the Mechanical, Civil, and long…
This edition covers:
- Cost: Rs.100 Cr.
- Project Event: The feasibility study is ongoing, and RFQ for the Mechanical, Civil, and long lead items Contractor will likely be released in November 2024. The work progresses through in-house efforts while the plant remains operational, with certain tasks being completed during shutdown periods. The project is expected to be completed by March 2025.
- Cost: Rs.100 Cr.
- Project Event: The project is still in the evaluation phase; the proposal for environmental clearance is likely to be submitted in Q4 2024. The RFQ for the feasibility study is likely to be released at the end of Q1 2025
The complete bulletin is available to subscribers.