Software update: Fertilizer update

Project Event: The Detailed Project Report (DPR) has been finalized, and internal discussions…

IndianPetroChem

This edition covers:

  • Cost : Rs. 100 Cr.
  • Project Event : The Detailed Project Report (DPR) has been finalized, and internal discussions are underway. The hiring process for the LSTK contractor is in progress, with the project expected to be completed by September 2025.
  • Cost : Rs. 10 Cr.
  • Project Event : The RFQ for the LSTK contractor is expected to be reissued in October 2024, following the cancellation of the previous one due to a shortage of qualified bidders.