Project Event: The Centre has pledged a Rs 500 crore investment to establish two Nano urea…
This edition covers:
- Cost : Rs 2000 Cr.
- Project Event : The project is currently in the early planning phase. The Request for Quotation (RFQ) for the Technology Licensor and the Project Management Consultant is expected to be issued in Q1 2025.
- Cost : Rs 500 Cr.
- Project Event : The Centre has pledged a Rs 500 crore investment to establish two Nano urea plants in July 2024. The project is in the initial phase, and the RFQ for the environmental consultant is likely to be released in November 2024 in place of September 2024, due to a delay in the internal discussion. The project has not submitted the proposal for environmental clearance yet.