Bulletin Updates
Project Event: The company has hired the KBR as the Detail Engineering Consultant, and the… – Software update: Fertilizer projects, 12 Jun 2024
Jun 12, 2024
Nitric Acid Brownfield Project
Cost:Rs 1950 crore
Project Event: The company has hired the KBR as the Detail Engineering Consultant, and the study is ongoing, RFQ for the LSTK contractor is likely to be released in Q3, 2024..
Phosphoric acid Expansion Project
Cost:Rs 50 crore
Project Event: The Company has obtained environmental clearance for the project. However, the company is facing budgetary issues in hiring the contractor, but internal discussions and negotiations are ongoing. It is likely to be finalized in Q3 2024.
Ammonia-Urea Expansion Project
Cost:Rs 6506 crore
Project Event: The Company has submitted the proposal for environmental clearance for the expansion with no increase in pollution load. The company is likely to release the RFQ for the PMC contractor in Q3 2024.
Methanol Storage Tank Greenfield Project
Cost:Rs 25 crore
Project Event: The 40 % of the construction work has been completed, the Tank Foundations and Supports works has been completed, Installation of tank is ongoing, also pipe connection work is ongoing, The project is likely to be commissioned at the end of 2024.