Bulletin Updates

Project Event: 60% of the construction work has been completed. The foundations for the… – Software update: Fertilizer projects, 6 Jun 2024

Jun 06, 2024

Effluent Treatment Plant Greenfield Project

Cost:Rs 100 crore

Project Event: A letter inviting bids has been released for an LSTK contractor, whose bid due date is July 16, 2024.

Briquette Fired Boiler Green field Project

Cost:Rs 27 crore

Project Event: Three companies are in the race for the miscellaneous civil works contract. The technical bid has been opened and the evaluation is ongoing. The detailed engineering study is also in progress. The RFQ (Request for Quotation) for the long lead items is likely to be initiated at the end of Q3 2024.

Ammonia-Urea Brownfield Project

Cost:Rs 16372 crore

Project Event: 60% of the construction work has been completed. The foundations for the syngas compressor, CO2 compressor, and ammonia refrigerant deck have been finished. Out of the 13 km water pipeline from the Brahmani River, 6 km had been completed by May 2024. Out of the planned 121-meter height, 70 meters of the Prilling Tower have been erected. For the Air Separation Unit, the erection of the lower distillation column and exchanger in Cold Box A and Cold Box B has been completed.

Coal to Ammonium Nitrate Greenfield Project

Cost:Rs 11782 crore

Project Event: The Request for Quotation (RFQ) for the Lump-Sum Turnkey (LSTK) contractor has been released, and the bid due date is August 26, 2024.