Bulletin Updates

Software update: Fertilizer projects: Cost: Rs 1000 crore, Cost: Rs 470 crore, Cost: Rs 104 crore and 3 more – 24 May 2024

May 24, 2024

Phosphoric acid/Sulphuric acid Greenfield Project

Cost: Rs 1000 crore

A series of technology tie-ups have been done

Find out more

Urea Revamp Project

Cost: Rs 470 crore

The project is in its initial phase, and the RFQ for the technology license is likely to be revised in Q3 2024.

SSP/Phosphoric Acid/ Sulphuric Acid Greenfield Project

Cost: Rs 104 crore

The project is under environmental clearance; TOR has been granted, and environmental clearance is likely to be elicited at the end of Q4 2024. The company is likely to release the RFQ for the contractor in Q3 2024.

Urea Synthesis Reactor Revamp Project

Cost: Rs 100 crore

Project Event: The bid due date for the supply of a urea-synthesized reactor has been extended again from May 21 to June 26, 2024, due to a lack of suitable bidders.

Cost: 2700 crore

Project Event: The company has applied for an amendment in Environmental clearance, which is under examination; the project is likely to release the RFQ for the project management consultant in Q4, 2024.

DAP Expansion Project

Cost: 649 crore

Project Event: The company has applied for environmental clearance for the modernization of DAP Plants for the production of multi-grade complex fertilizers with no increase in pollution load. The project is under evaluation and is likely to elicit environmental clearance in November 2024. RFQ for the LSTK contractor is likely to be released in Q3 2024