Bulletin Updates

APS/DAP/Sulphurifc Acid Expansion Project8Cost:Rs 281 crore8Project Event: The company has… – Software update: Fertilizer projects, 21 May 2024

May 21, 2024

APS/DAP/Sulphurifc Acid Expansion Project
8Cost:Rs 281 crore
8Project Event: The company has applied  forthe transfer of EC from EID Parry (India) Ltd. to Coromandel International Limited for Expansion and Modernization of Compound Fertilizer Complex, which is under examination. It is likely to be a successful transfer at the end of Q3 2024. The RFQ for the LSTK contractor is likely to be released at the end of Q4 2024.
Phosphate Rich Organic Manure Greenfield Project
8Cost:Rs 100 crore
8Project Event: The project is still in the initial phase; the RFQ for the feasibility study is likely to be released at the end of June 2024, in place of April 2024, due to a lack of internal approval.
SSP/GSSP Greenfield Project
8Cost:Rs 16 crore
8Project Event: The project is under environmental clearance. It is likely to be elicited at the end of 2024, and the RFQ for the equipment and services is likely to be released in Q1 2025.
NPK/DAP & Captive Power Plant Expansion Project
8Cost: Rs 500 crore
8Project Event: The feasibility study is still ongoing; the study has been delayed due to the impact of the gas leak at Ennore Plant. the study is likely to completed at the end of July 2024. The RFQ for the LSTK contractor is likely to be released in Q4 2024.
DAP Greenfield Project
8Cost: Rs 200 Crore
8Project Event: The negotiations with the local contractor are still ongoing, and finalization has been delayed due to a lack of internal approval. The project needs necessary approvals from senior management and board members to hire the contractor.

The full story is for subscribers. Log in to read it, or start a free trial.