Bulletin Updates

Project Event: The bid deadline for connecting to TFL's grid to supply 90 MW power through… – Software update: Fertilizer projects, 13 Feb 2024

Feb 13, 2024

Ammonia-Urea Brownfield Project

Cost: Rs. 16372 crore

Project Event: The bid deadline for connecting to TFL's grid to supply 90 MW power through line in line out has been extended from 6th Feb to 20th Feb 2024, due to the absence of suitable bidders. Additionally, the RFQ for constructing a 220 kV Lilo GIS has been pushed to 16th Feb 2024, from its initial deadline of 5th Feb.

Ammonia-Urea Annual Maintenance Project

Cost: Rs. 1.50 crore

Project Event: The RFQ for miscellaneous civil maintenance works for the factory for the year 2024–April 2025 has been issued, and the bid due date is February 29th, 2024.