Bulletin Updates
Project Event: The project is still on hold due to lack of funds and is likely to be resumed… – Software update: Fertilizer projects, 2 Jan 2024
Jan 02, 2024
Single/Triple Super Phosphate Greenfield Project
Cost: Rs. 25 crore
Project Event: The project is still on hold due to lack of funds and is likely to be resumed in Q2 2024.
Coal based Ammonia Greenfield Project
Cost: Rs. 200 crore
Project Event: Internal discussions for the RFQ for the BOO contractor is ongoing, and the release is expected by March 2024.