Project Event: The last date for bid submission for the RFQ for the Design, Engineering… – Software update: Fertilizer projects, 13 Dec 2023
Dec 13, 2023
DCS and ESD System Installation
Cost: Rs. 50 crore.
Project Event: The last date for bid submission for the RFQ for the Design, Engineering, Supply, Installation, and Commissioning of DCS and ESD System for the Urea Plant is 13th January 2024.
Nitric Acid Plant Expansion Project
Cost: Rs 200 crore
Project Event: Ongoing tech evaluation for Mono Medium Pressure Nitric Acid plant study by Casale SA, KBR, and Thyssenkrupp. Final decision expected by Q1 2024.