Bulletin Updates

Project Event: The due date for the bid submission for the Construction of 2 X 33kV Overhead… – Software update: Fertilizer projects, 8 Dec 2023

Dec 08, 2023

Ammonia-Urea Brownfield Project

Cost: Rs. 16,372 crore

Project Event: The due date for the bid submission for the Construction of 2 X 33kV Overhead Line has been extended from 30th November to 11th December 2023.

Ammonium Nitrate Melt Greenfield Project

Cost: Rs. 188 crore

Project Event: All essential long lead items have arrived on-site, with ongoing erection work. The project is set to be completed by September 2024.