RFQ for the EM works package is likely to be floated in Q1 2024 – Software update: Power projects, 1 Nov 2023

Nov 01, 2023

Rs. 1750 crore greenfield multipurpose project: RFQ ahead

Construction of HRT has been started.

Bid evaluation is in progress for the hydro-mechanical works.

RFQ for the EM works package is likely to be floated in Q1 2024

Rs. 490 crore greenfield hydel project: RFQ ahead

Forest clearance stage 1 has been granted

Construction of the approach road is in progress

Tariff issue has been resolved.

RFQ for the civil works package is likely to be floated in Q1 2024

Rs. 4542 crore greenfield pumped storage project: RFQ ahead

Geotechnical investigation and topographical survey works is yet to be started

Forest clearance stage -1 is under process at nodal office.

RFQ for the SIA consultant is likely to be floated in December 2023.