RFQ for the EM works package is likely to be floated in Q1 2024 – Software update: Power projects, 1 Nov 2023
Nov 01, 2023
Rs. 1750 crore greenfield multipurpose project: RFQ ahead
Construction of HRT has been started.
Bid evaluation is in progress for the hydro-mechanical works.
RFQ for the EM works package is likely to be floated in Q1 2024
Rs. 490 crore greenfield hydel project: RFQ ahead
Forest clearance stage 1 has been granted
Construction of the approach road is in progress
Tariff issue has been resolved.
RFQ for the civil works package is likely to be floated in Q1 2024
Rs. 4542 crore greenfield pumped storage project: RFQ ahead
Geotechnical investigation and topographical survey works is yet to be started
Forest clearance stage -1 is under process at nodal office.
RFQ for the SIA consultant is likely to be floated in December 2023.