2023: NPK/DAP & Captive Power Plant Expansion Project

Cost: Rs 500 crore

Project Event: The project is still under study, and the Environmental Clearance application has been filed. The request for quotation (RFQ) for the lump sum turnkey (LSTK) contractor is expected to be issued in the fourth quarter of 2023.

SSP-Sulphuric Acid & NPK Fertilizer Expansion Project

Cost: Rs 75 crore

The project has been delayed due to the challenges in procuring raw materials, The discussion is still ongoing with local contractor, finalization is likely to be completed In December 2023.