Project Event: The RFQ for miscellaneous civil work for the upcoming Cobalt Recovery Plant at… – Software update: Fertilizer projects, 12 Sep 2023

Sep 12, 2023

Ammonia-Urea Annual Maintenance Project

Cost: Rs 20 Cr.

Project Event: Rotodyne Engineering Services Pvt Ltd has been selected to undertake the lining contract for various jobs during the mechanical maintenance and restoration of the Gas Turbine Generator (GTG) during the shutdown of the HRSG Plant. The company will issue the tender in phases for different plants.

Trombay Cobalt Recovery Unit Greenfield project

Cost: Rs 100 Crore

Project Event: The RFQ for miscellaneous civil work for the upcoming Cobalt Recovery Plant at the HWB facility has been released, with the bid due date set for September 23, 2023.

Ammonium Nitrate Melt Greenfield Project

Cost:Rs 188 Cr.

Project Event: RFQ for End-to-End studies of Ammonium Nitrate Melt project is likely to be re-released in October 2023, previous RFQ was cancelled due to lack of suitable bidder. The Engineering service is performed by Casale. L&T Hydrocarbon is the LSTK contractor who supply Process license, Supply of Basic Design., Detailed Engineering, HAZOP Studies, and implementation of its recommendation., Procurement, and Supply of all equipment

Phosphoric acid Expansion Project

Cost: Rs 500 Crore

Project Event: RFQ for the LSTK contractor is likely to be released in Q4 2023. DE Smet Agro has been finalized for End-to-End study of Phosphoric acid plant capacity enhancement.

DAP/NPK /Phosphoric acid Greenfield Project

Cost: Rs 500 Cr.

Project Event: RFQ for the local contractor is likely to be released in Q4 2023, due to delay in the internal discussion. The Project has been elicited the environmental clearance in February 2023.

DAP Expansion Project

Cost: Rs 20 Cr.

Project Event: Internal discussion is still ongoing, RFQ for the LSTK contractor is likely to be released in Q4 2023. The project has elicited capital approval as well as environmental clearance.

Sulphuric acid Plant Greenfield Project

Cost: Rs 182 Crore

Project Event: The company has received the approval for the environmental clearance, RFQ for the LSTK contractor is likely to be released in Q4 2023.