Project Event: The studies as well as procurement are still ongoing, civil work is likely to… – Software update: Fertilizer projects, 4 Sep 2023
Sep 04, 2023
Technical Ammonium Nitrate Greenfield Project
Cost:Rs 1170 Cr.
Project Event: The studies as well as procurement are still ongoing, civil work is likely to be started in November 2023. The project is likely to be completed at the end of 2025. The Company has hired the L& T hydrocarbon for Technology licensor as well as for Engineering, Procurement and Construction
Ammonia/Nitric Acid/SOP Greenfield Project
Cost:Rs 200 Crore
Project Event: The discussion is still ongoing for the hiring of a contractor, The company is likely to be hire a contractor in Q4 2023.