Ammonia-Urea Brownfield Project8Cost: Rs 6500 croreMore contracting onSSP Expansion… – Software update: Fertilizer projects, 3 Aug 2023
Aug 03, 2023
Ammonia-Urea Brownfield Project
8Cost: Rs 6500 crore
More contracting on
SSP Expansion Project
8Cost: 21 Cr.
8Project Event: The project requires additional land and is awaiting approval from the authorities. Environmental clearance is likely to be elicited in September 2023. Negotiations with local contractors regarding equipment and services are currently in progress
Ammonia-Urea Brownfield Project
8Cost: Rs 6500 crore
An update on contracting
Single Super Phosphate Expansion Project
8Cost: 20 crore.
8Project Event: The detailed engineering part has been completed and the construction work and installation of long lead items are ongoing. The project is likely to be commissioned in December 2023.