The civil works(lot-1) contractor has completed the mobilization of equipment. – Software update: Power projects, 19 Jul 2023
Jul 19, 2023
Rs. 950 crore greenfield hydroelectric project: RFQ ahead
The civil works(lot-1) contractor has completed the mobilization of equipment.
Bid evaluation is in progress for the civil works package (lot-2).
RFQ for the EM works package will likely be floated in Q4 2023
Rs. 11030 crore greenfield pump storage project: RFQ ahead
Bid evaluations are in progress for the electro-mechanical works package
RFQ for the civil and HM works package is likely to be floated on August 2023
Rs. 4500 crore greenfield hydroelectric project: RFQ ahead
The civil works contractor has been selected.
Bid evaluation is in progress for the HM works.
RFQ for the EM works package is likely to be floated in September 2023