RFQ for the EM works package is likely to be floated in Q3 2023 – Software update: Power projects, 7 Jun 2023
Jun 07, 2023
Rs. 885 crore greenfield hydroelectric project: RFQ ahead
The civil works contractor has started the construction.
Bid evaluation is in progress for the HM package.
RFQ for the EM works package is likely to be floated in Q3 2023
Click here for more details
Rs.1500 crore greenfield pumped storage project: RFQ ahead
The PFR and DPR consultant has been selected.
Bid evaluation is in progress for the EIA consultant.
RFQ for the SIA consultant is likely to be floated in Q3 2023
Click here for more details
Rs. 7630 crore greenfield off-Stream closed loop pumped storage storage project: RFQ ahead
The TOR has been granted.
EIA consultant has been selected.
RFQ for the SIA consultant is likely to be floated in Q3 2023.
Click here for more details
Rs. 9785 crore brownfield super-critical thermal power project: RFQ ahead
Pilling and foundation work for BTG has been completed
Contractor has been selected for the CHP civil works.
RFQ for the PT plant package is likely to be floated in July 2023.
Click here for more details
Rs. 11555 crore thermal power expansion project: RFQ ahead
The TEC has been approved
The tender has been floated for the EPC package of BOP works
RFQ for the BTG package is likely to be floated in Q3 2023.
Click here for more details
Rs.18000 crore greenfield pumped storage project: RFQ ahead
Bid evaluation is in progress for the CW system package.
Erection and installation of pressure parts for TG units are in progress.
RFQ for the DM plant package is likely to be floated in Q3 2023.
Click here for more details