The civil package for this Rs 5800 crore multi-purpose project was awarded to L&T – Software update: Power projects, 1 Jun 2023

Jun 01, 2023

This Rs. 5700 crore hydel project has completed all its preparatory work: TEC has been granted but forest clearance stage-2 is to be cleared

EC submission is in progress

And civil package, combining lot 1 and lot 2, is expected in July, 2023

Rs. 5800 crore multi purpose project : RFQ ahead

The civil package for this Rs 5800 crore multi-purpose project was awarded to L&T

But a write petition was filed though it was dismissed

Now the project promoter is trying to be extra careful, and the HM tender has been delayed

It is expected now in July

Rs 870 crore intermediate greenfield hydroelectric project: SIA works completed

The EIA / EMP report has been completed and it is yet to be approved by MOEF.

The hydrology report of the project has been approved

The SIA study was completed.

RFQ for the civil works package is likely to be floated in July 2023