The forest clearance stage 1 is under process at the nodal office. – Software update: Power projects, 13 Apr 2023
Apr 13, 2023
Rs. 6010 crore greenfield pump storage project: RFQ ahead
The forest clearance stage 1 is under process at the nodal office.
RFQ for the drilling and drifting works is likely to be floated in May 2023.
Rs. 8400 crore greenfield pump storage project: SIA works ahead
The EIA consultant has been selected.
RFQ for the SIA consultant is likely to be floated in June 2023
Rs. 4600 crore greenfield pump storage project: RFQ ahead
TOR has been granted.
Bid evaluation is in progress for the EIA package.
RFQ for geotechnical investigation and topographical survey is likely to be floated in May 2023