Project Event: The hiring process of local contractor is still ongoing; the company is… – Software update: Fertilizer projects, 6 Apr 2023
Apr 06, 2023
GSSP/GBSSP/GZSSP/GPG/BSP/BSG Expansion Project
Cost: Rs 48 Crore
Project Event: The hiring process of local contractor is still ongoing; the company is talking with different contractors. It is likely to be finalized in May 2023.
DAP: Rs 300 Cr.study
Project Event: The Feasibility has been completed, RFQ for the LSTK contractor is likely to be released in June 2023.The PDIL has been selected for the preparation of the Techno-Economic Feasibility Report. Based on the feasibility report of PDIL, future action shall be planned.