Rs. 900 crore greenfield hydroelectric project: Civil works ahead
Forest clearance stage 1 has been approved.
PMC has been selected
RFQ for the civil works package is likely to be floated in May 2023
Rs. 857 crore greenfield hydroelectric project: RFQ ahead
Wildlife clearance has been granted
Pre-bid meeting has been completed for the civil works package (lot-1).
RFQ for the civil works package (lot 2) is likely to be floated in Q3 2023
Rs. 834 crore greenfield hydroelectric project: Civil works coming up
TEC has been approved by the CEA
Pre-bid meeting is yet to be conducted for the civil works package (lot-1).
RFQ for the civil works package (lot 2) is likely to be floated in June 2023.