Bulletin Updates
Project Event: Bid due date of End to End studies on the Ammonium Nitrate Melt project has… – Software update: Fertilizer projects, 17 Mar 2023
Mar 17, 2023
Ammonium Nitrate Melt Greenfield Project
Cost: Rs 188 Crore
Project Event: Bid due date of End to End studies on the Ammonium Nitrate Melt project has been extended from 16 March to 27 March 2023, due to lack of suitable bidder. The Engineering service is performed by Casale. L&T Hydrocarbon is the LSTK contractor
Urea Revamp Project
Cost: Rs 700 Cr.
Project Event: RFQ for the LSTK contractors is expected to be released in May 2023, The detailed engineering study is still ongoing by Fact Engineering And Design organization, and this is likely to be completed in April 2023.