RFQ for the EPC package is likely to be floated in Q3 2023. – Software update: Power projects, 10 Mar 2023
Mar 10, 2023
Rs. 4616 crore super-critical thermal power expansion project: EPC package coming up
Public hearing of the project has been completed by the state pollution control board
EC of the project has been delayed due to non-compliance with air quality parameters.
RFQ for the EPC package is likely to be floated in Q3 2023.
Rs. 5860 crore greenfield pumped storage project: RFQ ahead
TOR of the project has been granted.
RFQ for the EIA consultant is likely to be floated in April 2023
Rs. 6614 crore off-stream closed-loop pumped storage project: TOR granted
EIA consultant has been selected.
RFQ for the drilling and drifting works is likely to be floated in Q2 2023