Rs 960 crore greenfield hydroelectric project: EPC package coming up – 10 Mar 2023
Mar 10, 2023
Construction of HRT and TRT is in progress.
HM work contractor has started the construction.
Bid evaluation is in progress for the EM package.
RFQ for the EPC package for power evacuation is likely to be floated in Q2 2023.