RFQ for the HM package is likely to be floated in May 2023 – Software update: Power projects, 7 Mar 2023
Mar 07, 2023
Rs 5800 crore greenfield hydroelectric multipurpose project: HM package coming up
Contractor has been selected for the civil works package.
Mobilization of equipment at the site is yet to be started
Private land acquisition has been completed
RFQ for the HM package is likely to be floated in May 2023
Rs 3300 crore greenfield closed-loop pumped storage project: EIA consultant package
TOR of the project has been delayed due to a lack of a muck disposal plan
RFQ for the EIA consultant is likely to be floated in Q2 2023